Haryana regulator lets a private discom compete in Gurugram and Nuh
Haryana's electricity regulator has licensed a private company to distribute power alongside the State-owned distribution company (discom) in Gurugram and Nuh, giving over 8.3 lakh consumers a choice of supplier. Power staff have called a three-day strike.
What happened
The Haryana Electricity Regulatory Commission (HERC) on October 19 granted Eleven Power Private Limited a 25-year parallel distribution licence for Gurugram and Nuh under Section 14 of the Electricity Act, 2003. Over 8.3 lakh consumers, including households, farms, shops, industrial units and offices, can now choose between two discoms. The Haryana Electricity Employees and Engineers Joint Front called a three-day Statewide strike from Thursday. Power Minister Anil Vij said the decision was taken by an autonomous body despite the State's opposition to privatisation, and that it will be challenged before the Appellate Tribunal for Electricity.
Context
The licence area is growing fast. Projections in Eleven Power's petition, based on growth rates approved by HERC, show annual electricity sales rising from about 12,220 million units in FY 2024-25 to about 18,224 million units by FY 2030-31. Many commercial establishments, industrial units and high-rise buildings still depend on diesel generators during outages. Across Haryana, nearly 1.3 lakh applications for new connections and load enhancement, involving over 2,400 MW of load, were pending as of October 2025. Eleven Power says it will build its network in phases over five years across all five divisions, with Nuh in the first phase.
Why it matters
A parallel licence brings competition into retail power supply, which is usually a local monopoly of one discom. Under Section 14, a second licensee can supply the same area through its own network, so consumers can switch if service is poor. The risk lies in cross-subsidies. Indian discoms commonly charge commercial and industrial users more so that farm and poor-household supply can be priced lower. The Joint Front says the licence hands high-revenue areas of the State-owned Dakshin Haryana Bijli Vitran Nigam to a private player. If the best-paying consumers move, less revenue is left to fund subsidised supply. Eleven Power has committed to supply all consumer categories without discrimination and to connect anyone who applies.
Impact for India
- Consumers in Gurugram and Nuh: over 8.3 lakh households, farms, shops and offices get a choice between two discoms.
- Businesses relying on diesel back-up: a second network could improve reliability where outages force generator use.
- Dakshin Haryana Bijli Vitran Nigam: the Joint Front says it stands to lose high-revenue areas.
- Farmers and poor households in Nuh: the Bharatiya Kisan Union says subsidised supply is at risk because the government has given no written assurance that subsidies will continue.
- Haryana government: it opposes the order and will appeal to the Appellate Tribunal for Electricity; the Joint Front will announce its next steps on October 24.
Key data
Concepts
Theory lens
Natural monopoly and contestable markets — a power distribution network has high fixed costs, so one supplier is usually cheapest, and that supplier is regulated rather than exposed to competition. A parallel licence tries to make the market contestable by letting a rival build its own network. HERC is betting that demand rising from about 12,220 million units to about 18,224 million units can support two networks without leaving the incumbent with only the loss-making consumers.
Stakeholders
Practice Question — from the story
With reference to the parallel electricity distribution licence granted in Haryana, consider the following statements:
- The licence was granted under Section 14 of the Electricity Act, 2003, and lets over 8.3 lakh consumers in Gurugram and Nuh choose between two discoms.
- Eleven Power has committed to supply electricity on request under Section 43 of the Act and to build its network in phases over five years.
Which of the statements given above is/are correct?
Reveal answer & explanation
Answer: Both 1 and 2
- Statement 1: Correct because HERC's October 19 order grants the licence under Section 14, and over 8.3 lakh consumers in Gurugram and Nuh can now choose between two discoms.
- Statement 2: Correct because Eleven Power's petition commits to supply on request under Section 43 and to build the network in phases over five years across all five divisions.
Therefore, the correct answer is Both 1 and 2.
Concept check — test your understanding
Why could a State-owned discom's finances suffer when a parallel licensee enters its highest-revenue urban areas?
Reveal answer & explanation
Answer: B
- A cross-subsidy relies on high-paying consumers; if they switch, the incumbent has less revenue to fund lower tariffs for farms and poor households.
- A parallel licensee builds its own network rather than taking over the incumbent's assets.
- Wheeling charges are paid for using someone else's network, not by the incumbent to an entrant that uses its own.
- Eleven Power has committed to supply on request under Section 43, so the risk of losing the best-paying users works through consumer choice, not a legal exemption.