Cabinet approves ₹14,500 crore support for 92 GWh of grid storage
The Cabinet approved ₹14,500 crore in viability gap funding, a grant that makes projects affordable, for 92 GWh of grid-scale energy storage by 2030-31.
What happened
The Union Cabinet on November 4 approved a ₹14,500 crore Viability Gap Funding (VGF) scheme for grid-scale energy storage, running from 2026-27 to 2030-31. It supports 92 GWh of new capacity: 60 GWh of pumped hydro, 30 GWh of batteries and 2 GWh of other technologies. Total investment is estimated at ₹97,600 crore. Capacity will be awarded through tariff-based competitive bidding. Public and private electricity distribution companies can get support for battery and pumped hydro projects. Battery projects must meet a minimum domestic content requirement of 40%.
Context
India has around 54 GWh of grid-scale storage and a target of 411 GWh by 2031-32. The new capacity equals 170% of today's capacity. The Power Ministry already runs two VGF schemes for batteries, covering 43.8 GWh with ₹9,160 crore of support. The first began at 4 GWh with ₹3,760 crore. It grew to 13.8 GWh on the same budget after battery prices fell. As of July, 0.5 GWh under that scheme had been commissioned and ₹168.04 crore had been paid.
Why it matters
Solar and wind produce power when the weather allows, not when people need it. Storage moves that power to the hours of demand. Without it, surplus power is wasted: 1,835 million units of renewable power were curtailed in July and August, according to the Centre for Research on Energy and Clean Air. A VGF grant covers the gap between a project's cost and what buyers will pay. Bidding on the tariff then lets competition show how large that gap really is. The earlier rounds show two risks. Falling battery prices can stretch a fixed grant, as 4 GWh became 13.8 GWh. But awards are not delivery: financial closure covered 6.54 GWh of that capacity by July. The domestic content rule adds a trade-off. It supports Indian battery makers, but it can raise project costs if local parts cost more than imports.
Impact for India
- Distribution companies: public and private companies can get support for battery and pumped hydro projects through tariff-based bidding.
- Battery makers: the 40% domestic content rule adds demand, on top of existing supply-side incentives for battery manufacturing.
- Pumped hydro developers: 60 GWh of the 92 GWh is planned as this technology.
- Renewable generators: more storage gives surplus power somewhere to go, which can ease curtailment.
- Public finances: ₹14,500 crore of support is meant to bring in a total investment of ₹97,600 crore.
Key data
Concepts
Theory lens
Peak-load pricing — when a good is costly to store, its cost of supply differs by hour, so the price should differ by hour too. Storage narrows that gap by moving cheap surplus power to the peak. The ₹14,500 crore grant is public money for building that bridge, with bidding used to find the lowest tariff at which it can run.
Stakeholders
Practice Question — from the story
With reference to the Viability Gap Funding scheme for grid-scale energy storage approved by the Union Cabinet, consider the following statements:
- The scheme supports 92 GWh of new capacity, of which 60 GWh is pumped hydro storage.
- Battery projects under the scheme must meet a minimum domestic content requirement of 40%.
Which of the statements given above is/are correct?
Reveal answer & explanation
Answer: Both 1 and 2
- Statement 1: Correct. The 92 GWh is made up of 60 GWh of pumped hydro, 30 GWh of batteries and 2 GWh of other technologies.
- Statement 2: Correct. The government set a minimum domestic content requirement of 40% for battery projects.
Therefore, the correct answer is Both 1 and 2.
Concept check — test your understanding
A government offers viability gap funding to a storage project and awards it through tariff-based bidding. What does the grant mainly do?
Reveal answer & explanation
Answer: B
- VGF is a grant that closes the gap between a project's cost and its expected revenue, and bidding reveals how much support is needed.
- A describes cost-plus regulation. C describes a concessional loan, which must be repaid. D describes a compensation scheme, not a capital grant.