BusinessInfrastructure > HighwaysIndian EconomyInfrastructurePublic Expenditure

Lowest bidder walks away, stalling a 35.4 km Delhi-Mumbai Expressway stretch

The National Highways Authority of India (NHAI) is seeking bids a fourth time for a 35.4 km Gujarat stretch of the Delhi-Mumbai Expressway, after the lowest bidder, who quoted over 10% below the Rs 1,476 crore estimate, refused the award.

What happened

NHAI has issued a second call for bids for package 8, the 35.4 km Jujuwa-Gandeva section in Valsad and Navsari districts, after the lowest (L1) bidder, Bansal Construction Works, declined the letter of award. The firm had quoted over 10% less than the estimated project cost of Rs 1,476 crore, and NHAI encashed its bid security of Rs 14.76 crore. Bids closed on October 13. This is the fourth time NHAI has invited bids for the stretch, whose balance work is only 4.85% complete. Completion is now targeted for June 30, 2028.

Context

The 1,386-km expressway, in 53 packages across Delhi, Haryana, Rajasthan, Madhya Pradesh, Gujarat and Maharashtra, is being built at a cost of Rs 1.04 lakh crore. Of the Rs 1,03,636 crore project cost, Rs 71,718 crore had been spent by December 2025. Package 8 was first awarded in 2021 under the Hybrid Annuity Mode (HAM), terminated in March 2023, and re-awarded to the same contractor in November 2023 under Engineering, Procurement and Construction (EPC), before being terminated again. Nearby, package 9 is around 22% complete and package 10 has 36.23% physical progress.

Why it matters

The stretch shows how aggressive bidding can raise the real cost of public infrastructure. In a lowest-price tender, a firm that underbids may win a contract it cannot carry out. Each failed award adds a fresh tender cycle and more delay. The second-lowest bid here, from Ceigall India, was Rs 1,581 crore, above the estimate. NHAI's answer is contractual: a July 15 circular requires additional performance guarantees from bidders, so a firm that quotes too low has more at stake. The package has also moved between contract models. Under HAM the developer shares the financing burden, while under EPC the authority pays for construction and the contractor only builds.

Impact for India

  • NHAI: another tender cycle for package 8, with the Rs 14.76 crore bid security forfeited by the L1 bidder.
  • Contractors: the July 15 circular on additional performance guarantees raises the cost of quoting unrealistically low.
  • Freight and road users: the full expressway is meant to cut the Delhi-Jawaharlal Nehru Port distance by 180 km and travel time by up to 50%, and three small Gujarat stretches adding up to 87 km are holding that back.
  • Public investment: Rs 71,718 crore of the Rs 1,03,636 crore cost had been spent by December 2025, while the delayed packages defer the corridor's full use.

Key data

Estimated cost of package 8: Rs 1,476 croreL1 quote over 10% lower; second-lowest Rs 1,581 crore
Bid security encashed: Rs 14.76 crore
Progress on package 8 balance work: 4.85%Completion targeted for June 30, 2028
Expressway spending to December 2025: Rs 71,718 croreOf Rs 1,03,636 crore project cost

Concepts

Hybrid Annuity Mode (HAM)A highway contract in which the government pays part of the cost during construction and the developer raises the rest, recovering it through annuity payments over the operating period.Package 8 was first awarded under HAM in 2021.
Engineering, Procurement and Construction (EPC)A contract in which the government pays the full construction cost and the contractor designs and builds the project without financing it.The stretch was re-awarded under EPC in November 2023 after the HAM contract was terminated.
Performance guaranteeSecurity a contractor deposits that the authority can forfeit if the contractor fails to perform.NHAI's July 15 circular asks for additional guarantees to deter aggressive bids.

Theory lens

Winner's curse in procurement auctions — when contracts go to the lowest bid, the winner is often the firm that most underestimated costs, and it may abandon the work once those costs become clear. Bansal Construction quoted over 10% below the Rs 1,476 crore estimate and then declined the award. NHAI's July 15 circular on additional performance guarantees raises the price of such a bid, which is the standard contractual fix for abnormally low tenders.

Stakeholders

Gains: NHAIRecovered Rs 14.76 crore by encashing the defaulting bidder's bid security.
Pressure point: Bansal Construction WorksLost its bid security after declining the award.
Pressure point: Freight operators and road usersFace further delay in the full Delhi-Mumbai corridor.

Practice Question — from the story

With reference to package 8 of the Delhi-Mumbai Expressway, consider the following statements:

  1. NHAI encashed a bid security of Rs 14.76 crore after the lowest bidder declined the letter of award.
  2. The stretch was first awarded in 2021 under the Engineering, Procurement and Construction mode and later re-awarded under the Hybrid Annuity Mode.

Which of the statements given above is/are correct?

  1. 1 only
  2. 2 only
  3. Both 1 and 2
  4. Neither 1 nor 2
Reveal answer & explanation

Answer: 1 only

  • Statement 1: Correct because the NHAI official said the bid security of Rs 14.76 crore was encashed under the request for proposal after Bansal Construction did not accept the award.
  • Statement 2: Incorrect because it is the reverse: the stretch was first awarded under the Hybrid Annuity Mode in 2021 and re-awarded under the Engineering, Procurement and Construction mode in November 2023.

Therefore, the correct answer is 1 only.

Concept check — test your understanding

How does the Hybrid Annuity Mode (HAM) of highway contracting differ from the Engineering, Procurement and Construction (EPC) mode?

  1. Under HAM the developer finances part of the project and is repaid by the government in instalments, while under EPC the government pays the full construction cost and the contractor only builds.
  2. Under HAM the developer collects tolls and bears all traffic risk, while under EPC the contractor is repaid through annuities.
  3. HAM is used only for projects funded by multilateral lenders, while EPC is used for projects funded from the domestic budget.
  4. Under HAM the government bears no financing cost during construction, while under EPC the contractor arranges all of the financing.
Reveal answer & explanation

Answer: A

  • HAM splits the financing between the authority and the developer, who is repaid through annuities, whereas EPC is fully government-funded with the contractor bearing construction risk only.
  • Toll collection with traffic risk describes the build-operate-transfer toll model, not HAM, and EPC contractors are paid for construction, not annuities.
  • The choice between HAM and EPC depends on how financing and risk are shared, not on whether a multilateral lender is involved.
  • This reverses the two models: the government pays part of the cost during construction under HAM and all of it under EPC.